Foundation Plan — Top View
ISOLATED FOOTINGS AT ALL 12 COLUMN POSITIONS | TIE BEAMS ALONG GRID LINES | ALL DIM IN mmSection X–X — Foundation Detail
THROUGH GRID LINE 3 | SHOWING FOOTING DEPTH, PCC, TIE BEAM, PLINTH | NOT TO SCALELegend
Isolated Footing (RCC)
PCC Bed (M10, 100mm)
Tie Beam (300×450mm)
RCC Column (300×300mm)
Plinth Wall / Boundary
Soil / Excavation Zone
Footing Schedule
| Mark | Size (mm) | Depth | Qty | At |
|---|---|---|---|---|
| F1 | 1200×1200 | 450mm | 8 | A&C rows |
| F2 | 1400×1400 | 450mm | 4 | B spine |
| PCC | Ftg+300 | 100mm | 12 | All ftgs |
F2 (central spine) is larger
as B-columns carry higher load
from both adjacent bays.
Depth Schedule
Excavation Depth (BGL)1800 mm
PCC Thickness (M10)100 mm
Footing Thickness450 mm
Footing Top → NGL1250 mm
Plinth Height (NGL)+450 mm
Tie Beam Size300 × 450
GF Slab Thickness125 mm
Col. Stub (BGL)1250 mm
Column Size300 × 300
Clear Cover (Ftg)50 mm
Clear Cover (Beam)40 mm
Material Specs
PCC GradeM10
Footing GradeM20
Tie Beam GradeM20
Column GradeM20
Steel (Ftg)Fe 415
Steel (Beam/Col)Fe 500
SBC Assumed150 kN/m²
Quick Stats
12
Footings
1.8m
Depth BGL
M20
Concrete
F1+F2
Footing Types
+450
Plinth mm
G+2
Future Ready
Engineering Notes
· SBC 150 kN/m² assumed for normal soil
· Increase depth to 2.0m if black cotton soil
· Anti-termite treatment before PCC
· Waterproofing coat on footing sides
· B-column footings (F2) sized for central spine load
· Tie beams prevent differential settlement
· All dims to be verified by structural engineer
· SBC 150 kN/m² assumed for normal soil
· Increase depth to 2.0m if black cotton soil
· Anti-termite treatment before PCC
· Waterproofing coat on footing sides
· B-column footings (F2) sized for central spine load
· Tie beams prevent differential settlement
· All dims to be verified by structural engineer