Structural Engineering · Drg No. MHSS-07 · Staircase
STAIRCASE REINFORCEMENT DETAILS
Mayank's House · G+1 Residential · Waist Slab 150mm · 12 Risers · T10@150 Main · M20/Fe500 · IS 456:2000
Waist: 150mm
Riser: 175mm
Tread: 250mm
T10@150 Main
T8@200 Dist.
T10@150 Top
T8@150 Stir.
DRG. NO. MHSS-07
DATE: 01.03.2026
SCALE: NTS
REV: 00
Plan + Location
Longitudinal Section
Cross-Section & Details
Landing & Supports
BBS + Notes

Staircase Location Plan & Geometry

Sheet 1 of 5
Single-flight dog-leg stair · GF to FF (+3000mm) · 12 risers × 175mm · 11 treads × 250mm · Waist slab 150mm
175
Riser mm
250
Tread mm
12
No. Risers
11
No. Treads
150
Waist mm
3000
Floor–Floor
1200
Width mm
2750
Horiz. span

STAIRCASE PLAN — GROUND FLOOR LEVEL

SCHEMATIC LOCATION IN BUILDING PLAN · 1200mm CLEAR WIDTH · NOT TO SCALE
BUILDING OUTLINE (7600 × 11045mm) UP FF LANDING +3000mm GF LANDING ±0.00 STRINGER WALL/BEAM STRINGER WALL/BEAM C C C C Clear width = 1200mm Horiz. span = 2750mm STAIRCASE GEOMETRY No. of Risers: 12 × 175mm No. of Treads: 11 × 250mm Clear Width: 1200mm Horiz. span: 2750mm (11×250) Vertical rise: 2100mm (12×175) Landing GF: 600mm deep Landing FF: 750mm deep Waist slab: 150mm Riser + 2×Tread: 675mm ≈ 600–660 ✓ Slope angle: 34.9° (tan⁻¹ 175/250) Inclined length: 3341mm Effective span: ~3000mm (IS 456) REINFORCEMENT Main bars: T10 @ 150mm Dist. bars: T8 @ 200mm Top bars: T10 @ 150mm Cover: 20mm Concrete: M20 (fck=20 N/mm²) Steel: Fe500 (fy=500 N/mm²) LL: 3.0 kN/m² (IS 875)
Tread lines (250mm)
Landing slab
Stringer/support
Columns

DESIGN PARAMETERS

IS 456 · WAIST SLAB METHOD
ParameterValueCheck
Riser (R)175mm150≤R≤200 ✓
Tread (T)250mm200≤T≤300 ✓
R + 2T175+500=675600–660mm ✓
No. Risers12 nos.
No. Treads11 nos.
Floor–Floor3000mm12×250=3000 ✓
Horiz. span2750mm11×250mm
Waist slab150mmSpan/20=138 ✓
Clear width1200mm≥1000 ✓
Eff. span Le~3000mmIncl. landing
Total load w~12.4 kN/m²DL+LL+step
Mu (midspan)~13.95 kNm/mwLe²/8
Ast req.~330 mm²/mT10@150=524 ✓
Ast prov.T10@150 = 524mm²/mOK ✓
Dist. steelT8@200 = 251mm²/m0.12% ✓
Cover20mmExposed top
d effective125mm150−20−5
Loading calculation (per IS 456):
DL waist: 0.15×25/cosθ = 4.56 kN/m²
DL steps: R/2×25 = 2.19 kN/m²
Finishes: 1.0 kN/m²
LL: 3.0 kN/m²
Total factored: ~12.4 kN/m²

Longitudinal Section — Stair Flight

Sheet 2 of 5
Section through stair flight showing waist slab · 12 risers 175mm · 11 treads 250mm · main + distribution bars · landing details

SECTION A–A — LONGITUDINAL THROUGH FLIGHT (GF +0.00 TO FF +3.00m)

WAIST SLAB 150mm · T10@150 MAIN BARS · T8@200 DIST. BARS · T10@150 TOP AT SUPPORTS · SCALE NTS
GF LANDING 150mm ±0.00 FF LANDING 150mm +3000mm SUPPORT BEAM/WALL SUPPORT BEAM T10 @ 150 MAIN BARS (T8@200 dist. bars perpendicular) T10@150 TOP T10@150 TOP 175mm R 250mm T t=150 Horizontal span = 2750mm (11 × 250) Total rise = 2100mm (12×175) GF ±0.00 FF +3000
Waist slab + steps M20
T10@150 Main bars (bottom)
T10@150 Top bars @ supports
T8@200 Distribution bars
Landing slab 150mm

Cross-Sections & Step Detail

Sheet 3 of 5
Section B–B at mid-flight · Individual step detail · Bar arrangement · Cover · Effective depth · Kicker detail

SECTION B–B — ACROSS WIDTH

AT MID-FLIGHT · 1200mm WIDTH
SECTION B–B TREAD (250mm finish) T10 MAIN BARS @150 T8 DIST. BAR @200 150mm 1200mm clear width 20mm cover d=125mm WALL WALL 9 bars shown · spacing = 1200/(n−1) = 150mm

INDIVIDUAL STEP DETAIL

TREAD + RISER + WAIST SLAB · ENLARGED
STEP DETAIL (ENLARGED) T10 MAIN BAR (parallel to slope) 20mm T = 250mm R=175mm t=150mm 35° Nosing: 25mm overhang at tread front Anti-skid finish on tread surface

WAIST SLAB — SECTION & REBAR

PERPENDICULAR TO SLOPE · BAR LAYERS
WAIST SLAB SECTION (Perpendicular to slope) T10 @ 150mm MAIN (bottom) T8 @ 200mm DIST. BARS T10 @ 150mm TOP (@ supports only) NA t = 150mm d=125mm 20mm c @150 WAIST SLAB DESIGN Thickness t: 150mm Cover: 20mm d effective: 125mm Main: T10@150 (Ast=524mm²/m) Dist: T8@200 (Asd=251mm²/m)

Landing Slab & Support Details

Sheet 4 of 5
GF landing 150mm slab · FF landing 150mm slab · Support beam/wall connections · Continuity reinforcement

LANDING SLAB REINFORCEMENT — GF & FF

150mm THICK · T10@150 BOTH WAYS · SUPPORT CONDITIONS
LANDING PLAN — GF (±0.00) GF LANDING 150mm · T10@150 ↕ · T10@150 ↔ SUPPORT WALL / BEAM (230mm) STAIR FLIGHT (above) 600mm 1200mm (= stair width) FF LANDING REINFORCEMENT (+3000) FF LANDING 150mm · T10@150 · T8@200 FF BEAM / WALL SUPPORT

CONTINUITY REINFORCEMENT DETAIL

FLIGHT–LANDING JUNCTION
L/4 Ld ≥ 400mm into landing Main bars cont. into landing Top bars @landing extend L/4 into flight LANDING SLAB STAIR FLIGHT

STRINGER SUPPORT CONDITIONS

SIDE WALLS · EDGE SUPPORT
ItemSpecification
Stringer wall230mm brick / RCC wall both sides
Bearing length≥150mm on support beam
GF supportPB 300×450mm or ground beam
FF supportGB 230×450mm beam at landing
Lateral supportColumns A-1 & A-2 either end
Main bar anchorageLd = 400mm + 90° hook
Top bar extentL/4 from support face
Landing continuityContinuous with stair bars
Handrail wall150mm stub wall on waist slab

Bar Bending Schedule & Engineering Notes

Sheet 5 of 5 · Complete BBS
Complete bar schedule for flight + GF landing + FF landing · steel quantities · IS 456 compliance

COMPLETE BBS — STAIRCASE (FLIGHT + LANDINGS)

ALL BARS · QUANTITIES · WEIGHT
MarkItemBarPositionShapeCut Len (mm)No. BarsTotal mWt (kg)
STAIR FLIGHT — 150mm Waist Slab (incl. 1200mm wide)
SF-M1Flight main barsT10Bottom parallel slopeStr.+2-hook3850934.7m21.4
SF-D1Flight dist. barsT8Perp. to slope (bottom)Straight12502025.0m9.9
SF-T1Top bars @ GF endT10Top, 800mm from GF spt.Str.+hook98098.8m5.4
SF-T2Top bars @ FF endT10Top, 800mm from FF spt.Str.+hook98098.8m5.4
SF-A1Anti-crack barsT8Top perpendicularStraight12501012.5m4.9
GF LANDING SLAB — 150mm (1200 × 600mm)
GL-M1GF landing mainT10Bottom span directionStraight70096.3m3.9
GL-D1GF landing dist.T8Bottom perp. directionStraight125056.25m2.5
GL-T1GF landing topT10Top both directionsStraight700149.8m6.1
FF LANDING SLAB — 150mm (1200 × 750mm)
FL-M1FF landing mainT10Bottom span directionStraight85097.65m4.7
FL-D1FF landing dist.T8Bottom perp. directionStraight125056.25m2.5
FL-T1FF landing topT10Top both directionsStraight8501411.9m7.4
T10 Bars
Flight: ~32 kg
Landings: ~22 kg
≈ 54 kg
T8 Bars
Flight: ~15 kg
Landings: ~5 kg
≈ 20 kg
Concrete
Flight: ~0.82 m³
Landings: ~0.29 m³
≈ 1.11 m³
Total Steel
T10: 54 kg
T8: 20 kg
≈ 74 kg

ENGINEERING NOTES

IS 456:2000 · SP 16 · IS 875
Design: IS 456:2000 — Waist Slab Method (Cl. 33)
· Stair type: Single-flight spanning longitudinally
· Effective span: Le = 3000mm (clear + half bearing each end)
· Waist slab t = 150mm (span/20 = 138mm → 150mm adopted)
· Main bars: T10@150 parallel to slope at bottom
· Distribution: T8@200 perpendicular to span
· Top bars: T10@150 at each support (top face), L/4 extent
· Cover: 20mm — stair exposed to weather on tread surface
· Kicker block: 75mm at riser foot on each tread
· Main bars bent up at support with 90° hook, Ld ≥ 400mm
· Landing slab: T10@150 both ways (span + distribution)
· Construction: cast waist slab first, step brickwork/concrete after
· Nosing: 25mm overhang, rounded edge, anti-skid finish
· Handrail: 900mm height, provided on open side

CONSTRUCTION SEQUENCE

RECOMMENDED ORDER
#ActivityNote
1Set out stair incline, fix soffit shutteringSlope 34.9°
2Fix main bars T10@150 parallel to slopeSecure to chairs 20mm
3Fix dist. bars T8@200 crosswiseTie at intersections
4Fix top bars T10@150 at supportsExtend L/4 from face
5Pour M20 waist slab monolithicallyVibrate carefully
6Cast step risers after waist cures (7 days)Formwork per step
7Apply tread finish + nosingAnti-skid required
8Erect handrail after 28-day cure900mm min. height